Job title: Baxter Road Hotel – Civil Earthworks and Piling

Client: Roberts Co

Duration: 12 Weeks

Description of project: Cherrie Civil Engineering were engaged by Roberts Co to complete the civil earthworks, CFA piling, handling and disposal of contaminated fills, D&C sheet pile shoring, OSD tank installation and FRP of footings.
As a part of the works CCE had to manage working adjacent to the ARTC corridor and safely handle and dispose Acid Sulphate Soils throughout the site.

Scope:

Site Demolition
Cut to fill and build piling platform
Design & Construct 70 x CFA Piles
Design & Construct Sheet Piling
Bulk excavation including off-site disposal
Detailed excavation
FRP of footings

Value of Contract: $2 million

Project Period: September 2021 – November 2021